Every dashed line on the architect's life-safety plan is a question for the mechanical drawings: can this duct cross here, and what has to be in it when it does? Four pages. The first two cover the walls, the last two cover the dampers.
| Time | Section | What happens |
|---|---|---|
| 0:00–0:05 | Hook | Two questions for the room: "A 2-hour shaft. What's the damper rating?" (1½ h) and "What's the difference between a 1-hour fire barrier and a 1-hour fire partition?" Don't answer yet. |
| 0:05–0:20 | 1 · The fire side | Building section. Highlight fire wall → fire barrier → fire partition, then press D to run a duct through all of them. Same hour rating, different rules. |
| 0:20–0:30 | 2 · The smoke side | Hospital floor plan: smoke compartments, cross-corridor doors, 22,500 ft² and 200 ft. Press F to start a fire: the doors close, the dampers close, patients move sideways. |
| 0:30–0:42 | 3 · The dampers | FD / SD / FSD / CRD / corridor damper. Hours for fire (only 1½ or 3), leakage class for smoke (Class II, 250°F min.). What closes them, and what installing them commits us to. |
| 0:42–0:52 | 4 · Which damper? | Live examples: 1 h mech room in a sprinklered building (no FD), 2 h shaft (FSD 1½ h), toilet-exhaust subduct, apartment corridor transfer grille (FSD), hospital smoke barrier. Then the drawing playbook. |
| 0:52–1:00 | Recap & Q&A | Recap card at the bottom of page 4. |
Teaching reference, not a code substitute. Section numbers are IBC 2021 (IMC §607 mirrors §717). Verify against the adopted edition, local amendments, and the AHJ before relying on it for a design.